POWERGRID Successfully Commissions Transmission System for Arun-3 Nepal Hydroelectric Project

30 Mar 2026  by POWERGRID   

Power Grid Corporation of India Limited (Powergrid) informed the stock exchanges on March 27, 2026 that it has commissioned the “Transmission System for Power Evacuation from Arun-3 (900 MW) HEP, Nepal of M/s SAPDC – Indian Portion.” The asset has a commercial operation date (COD) of September 3, 2023. The intimation follows a tariff order issued by the Central Electricity Regulatory Commission (CERC) on March 10, 2026.

The project forms part of the SJVN Arun-3 Power Development Company Private Limited (SAPDC) scheme covering the Indian portion in the Eastern Region. It includes the Sitamarhi (Powergrid)–Dhalkebar (Nepal) 400 kilovolt (kV) double-circuit quad transmission line and two associated 400 kV line bays at the Sitamarhi substation.